Category CSR, Updates & Stories
January 2023
Energy transition at Feldhaus Klinker - Update
We've come a step closer to CO2-free brick production
One of our new compact stations (25t) was set up in the hall with two mobile cranes and great precision.
It contains a 2000 kVA transformer that manages approximately 2 MW of the ring main for the new photovoltaic system.
In total, there are two of these compact substations and three transformers in the factory.