Energy transition at Feldhaus Klinker
The Path to CO2-Free Brick Production
The EU is to be climate-neutral by 2050. In addition, greenhouse gas emissions are to fall by at least 55 percent below 1990 levels by 2030. These are the still-current targets pursued by the German government and the business associations. When these targets were defined, there was no coronavirus, supply chains were functioning, and natural gas was supplied from Russia on favorable terms.
Today we know that we must become independent of fossil fuels in order to be able to produce safely and in a climate-neutral manner in the long term. The most obvious solution for us: natural gas must be replaced by hydrogen. However, the production of hydrogen requires large amounts of electricity that are not available in such quantities on the market. Furthermore, if the goal of climate neutrality is pursued, only renewable electricity generation can be considered. For Feldhaus Klinker , the answer to the question of how this goal can be achieved quickly became clear: the existing hall roofs will be equipped with PV modules, as will additional open areas owned by Company. The use of wind energy is another option for generating "green electricity". The energy generated at the site is converted on site into "green hydrogen" by means of an electrolyzer and used for the operation of the three kilns.
The vision in figures:
- Long-term substitution of natural gas by means of green hydrogen
- For the transition phase, the hydrogen will initially be blended into the natural gas and used for the drying and firing process
- Production of “green hydrogen” using the company’s own 10-megawatt electrolyser powered by photovoltaics and wind energy
- Procurement of “green electricity” from energy suppliers for periods in which no in-house electricity can be generated, in order to operate the electrolyser at the best possible efficiency
- Maximum surface utilization for photovoltaics on roof and open areas on the company premises and nearby private areas of up to 25 ha with an energy yield of approx. 18 MWp
- Utilisation of the company’s own wind energy of up to 15 MWp
The Timeline:
- Quarter 2022
- Create technical feed-in capability for blending hydrogen at the central gas transfer station
- Quarter 2023
- Commissioning of the electrical infrastructure in the form of a 10 MW factory ring main with decentralised feed-in points for photovoltaics.
- Covering the first half of all company roof areas with photovoltaics, approx. 5 MWp
- Quarter 2023
- Installation of photovoltaic systems on the second half of all operational roof areas, approx. 4 MWp
- Quarter 2024
- Admixture of hydrogen
The starting signal for the energy transition has been given: the first 1,250 m² of solar modules have been installed on the roof areas.
Later, additional “green electricity” could be generated by wind power, as indicated in the image here.